REASONS FOR CLAIMS IN CONSTRUCTION CONTRACTS
- Due to an unbalanced contract.
- Due to causes for which owner/ employer is responsible.
- Due to causes for which contractor is responsible.
- Due to causes beyond the control of both sides.
DUE TO AN UNBALANCED CONTRACT
- Basic structure of contract is in favor of client and loaded against the contractor.
- Risk is unilaterally transferred to one side.
- Absence of Neutralization mechanism.
- Progress of project is not the basis of contract.
DUE TO CAUSES FOR WHICH OWNER/ EMPLOYER IS RESPONSIBLE
- Poor site investigation by the owner at the pre-tender stage.
- Delay in acquisition of land and delay in handing over the site to contractors in time, including non-availability of sufficient work-fronts during the execution of the project.
- Delay in issue of drawings by the owner.
- Delay in issue of owner issue materials by the client.
- Delay in releasing payments leading to cash-flow problems to the contractors.
- Organizational problems of the owner.
- Non co-operation from the owner/project authorities due to poor earnestness in the public owner system.
- Co-ordination and managerial problems of the owner.
- Deviations on the agreed terms and conditions of the agreements by the owner or non-fulfillment of contractual obligations.
- Delay in settlement of rates for extra items, additional items and revision of rates.
- Poor quantity surveying by the owner at the time of tender and heavy increase in the quantum/scope of work.
- Delay in settlement of claims.
- Delay in arbitration proceedings during the execution of project.
- Forcing the contractor to appoint a particular sub contractor for certain specific works.
- Delay in completion of earlier stage contracts and hence a delay in handing over the site.
- Paucity of funds with the owner, leading to non-payment of bills and dues which leads to cash-flow problems for the contractor.
- Delay in giving decisions other than above by the owner.
DUE TO CAUSES FOR WHICH CONTRACTOR IS RESPONSIBLE
- Poor rates quoted for a few or several or all items.
- Managerial problems of the contractor.
- Strikes, militancy of the labour, and other labour related problems in the contractor’s organization.
- Lockout by contractors.
- Delay in mobilizing the required resources in time.
- Due to Causes beyond the control of both sides
- Force majeure conditions like heavy rains, floods, snow, landslides, earthquake,
- Political problems, riots, bandhs, etc.
- Health hazards and non-availability of medical facilities.
- Engineering and technical problems not previously understood.
- Inter-state disputes.
- Obstruction by mafia-gangs.
- Law and order problems
- Local problems, obstruction by local population and not employment from the owner or the contractor.
- Non – availability of construction materials (cement, steel pipes, CGI sheets) in the market.
- Non-availability of appropriate and adequate labour.
No comments:
Post a Comment